Omniris vertical paper · October 2026

Construction: the site, measured every week

What general contractors, owners, data-center builders and earthworks firms fly drones for, how often, and to what accuracy — and, use case by use case, what Omniris does with those flights: measured progress against the design and the schedule, earthwork quantities with stated uncertainty, and a record that holds up when the numbers are questioned.

SiteBuilding pad and parking · weekly flight · 38.6 acres (15.6 ha)
SurveyRTK · NAD83(2011) · 6 checkpoints · vertical RMSE 0.09 ft (2.7 cm)
Earthworkvs design surface · cut 12,480 ± 310 yd³ · fill 9,960 ± 290 yd³ (9,542 / 7,615 m³)
Progress41 % complete vs 46 % planned · SPI(t) 0.89 · forecast finish 12 days late
SchedulePrimavera P6 XER returned · 37 activities updated · change list attached
Findings3 open · synced to Procore Observations
Recordevery flight, measurement, approval and export sealed in the chain of custody
Illustrative example values.

Summary

Construction is the industry that made the drone a site tool. More than a third of the contractor members in one 2026 trade-association survey fly drones, and four in five of those use them to monitor site progress [1]. Nearly every state transportation department that answered a national survey had used drones on highway construction [2]. The imagery is rarely the hard part any more. The hard part is everything after the flight: tying the survey to the design's coordinates, turning a map into quantities someone will pay against, getting percent complete into the schedule without retyping it, and keeping a record that survives a claim.

Omniris covers that path end to end for the work most construction flights are flown for:

A measured map every flight

Photos become an orthomosaic, surface and terrain models and, if wanted, a 3D model, filed under the site beside every earlier flight. Ground control and checkpoints give a measured accuracy, stated on the result.

Earthwork with error bars

Stockpiles, pits and cut/fill against a base or the design surface, each volume with a ± figure and tonnage. Save a boundary once and every later flight of the site is measured the same way.

Design and schedule in one place

IFC, DWG, DXF and DGN designs placed in their real coordinates; Primavera P6 and Microsoft Project schedules linked to the design objects that build them; progress measured, approved by a person, and written back into the schedule file.

Where the team already works

Deliverables sent to Procore and Autodesk Forma; findings kept in sync with Procore Observations and Forma Issues both ways; contours and surfaces exported as DXF and LandXML in State Plane.

A record that holds up

Every photo, result, measurement, approval and export carries a tamper-evident custody history, with signed certificates and legal holds when a dispute starts.

Flights on a schedule

Plan the mission, check the airspace, and in the cloud and data center editions, post a recurring weekly or monthly job for a pilot to fly.

Volumes carry their uncertainty and controlled maps their measured accuracy; what the results are, and are not, is set out in What the results claim, and what they don't.

How construction uses drones today

Who flies, and how much

How often sites are flown

There is no industry standard cadence. The cadences that are documented come from the purpose of the flight:

The missions

MissionTypical cadenceWhat the buyer expectsWhat governs it
Progress monitoringMonthly in documented agency practice [2]Orthomosaic and photos of the whole site, compared date by date; owner and lender reportsContract reporting requirements; the schedule's percent complete
Topography and earthwork quantitiesMonthly during earthwork, with a final quantity at completion [2]Surface and terrain models, cut/fill and net volumes, often for progress paymentAgency quantity and survey specifications; positional accuracy standards [6]
Stockpiles and materialsAs needed; one of the three most common DOT uses [2]Volumes and tonnage per pileThe owner's or supplier's inventory practice
Design against as-builtAt key pours, pads and gradesAn as-built survey [2] with the design overlaid; where the work is off grade or out of placeThe design model (BIM/CAD) and its tolerances
Schedule and pay-application progressEach update periodPhysical percent complete per activity or pay lineThe schedule (P6, Microsoft Project) [11] [12]; pay applications (AIA G702 / G703) [19]
Stormwater and erosion controlEvery 7 days, or 14 days plus after 0.25 in of rain [4]Condition of silt fence, inlet protection, stabilised areas and discharge pointsEPA 2022 CGP Part 4 or the state permit; inspection by a "qualified person" [4]
InspectionAs neededClose views of structures, silt fence, cranes and falsework, with less need for special access equipment or climbing [3]The inspection programme the work falls under
Site logistics and safetyAs neededLaydown, haul roads, access, perimeter and hazards seen from aboveThe site safety plan
Marketing and stakeholder mediaAs neededPhotos, video, walk-around 3D [1]None

Where drones replace a survey crew, and where they don't

Drones replace boots on the ground for many surveys, mapping large areas relatively quickly compared with traditional survey methods [3], and they reduce the need for temporary work zones, special access equipment and climbing in inspections [3]. Agencies that use them for quantities still run them as surveys: a North Carolina DOT photogrammetry unit report on a drone earthwork project, for example, documents field-surveyed ground control, independent checkpoints, and checkpoint errors in feet on NAD 83 and NAVD 88 [9]. Published comparisons put drone stockpile volumes within 1.5% to 3.3% of actual in a Clemson University study for South Carolina DOT [8], and within 4% of a terrestrial laser scan in a peer-reviewed study that found ground control improved the result [10]. Ground crews remain for control, for anything under tree cover or inside a structure, and for work that state law treats as land surveying (see Accuracy and standards).

Data center and mission-critical builds

Data centers stand out in US non-residential construction spending. Census Bureau figures put data center construction spending at $50.7 billion in April 2026, up 28.1% from a year earlier [13], and the Associated General Contractors' reading of the July 2026 figures shows data center spending up 57% year over year while other private office construction fell 11% [14]. The drone work on such a build is the work described in this paper: earthwork for the site and pads, then the progress of every slab, pier and equipment pad, reported to the owner.

Where the data ends up

Construction drone data has to reach the project-management platform the team already works in. Autodesk Construction Cloud was renamed Autodesk Forma from March 24, 2026 (Autodesk Build became Forma Build) [15]. Buyers expect drone deliverables and issues to arrive in the system their team already uses.

The pain points

Use case by use case: what Omniris does

Use caseWhat Omniris delivers
Weekly progress mapOrthomosaic, surface and terrain models filed under the site; step, swipe or fade through dates in the Site Navigator
Stockpile volumes and tonnageVolume tool with a choice of base, ± uncertainty and tonnage; saved boundaries re-measured every flight
Cut/fill between two datesMaterial added, removed and net, each with ±, and a change map, graded for alignment
Cut/fill against the designDesign surface as the volume base (design model, DXF, LandXML or GeoTIFF) and Compare's Design mode
BIM/CAD overlay on the as-builtIFC, DWG, DXF and DGN placed in their stated coordinates, over every flight on the map and in 3D
"Is it at grade?" per elementEach linked slab, pad or pavement measured against design height within a tolerance, on survey-grade flights
Schedule progress (P6, Microsoft Project)Import, link to design objects, measure, approve, roll up (percent complete, forecast, SPI(t), earned value), export physical percent complete back
Pay-application checks (G702 / G703)Measured, approved progress per schedule activity and earned value, for whoever reviews each pay application
Survey accuracy QAGround control, checkpoints with RMSE, an accuracy class on controlled stitches
Topography to the design teamDXF contours and surfaces, LandXML surfaces, in State Plane, UTM or the survey's own system
Drainage, ponding and slopeContours, slope, aspect, ponding and drainage paths
Stormwater (SWPPP) inspectionsRecurring flights on the inspection cadence, dated maps, findings at each failed control, terrain drainage and ponding
Site logistics and safetyDated maps, findings, and AI detection that finds the objects you name, checked by a person
Façade, roof and structure inspectionMeasurable 3D mesh, findings on the model, thermal maps for roofs
360° site panoramasDJI sphere panoramas stitched into a 360° view, free, and shareable by link
LiDAR surveysLAS/LAZ processing and classification, terrain, surface and contour products, and measuring in the point-cloud viewer
Change alertsEmail when a new flight changes the volume beyond a threshold
Owner and lender reportingStitch, progress, comparison and situation reports as PDFs; live read-only site links
Procore and Autodesk FormaSend deliverables; pick designs and schedules from them; findings two-way with Observations and Issues
Getting a recurring flight flownMission planning, airspace check and, in the cloud and data center editions, a recurring marketplace job

Progress monitoring and owner reporting

Progress monitoring is the most common reason contractors fly [1]. In Omniris a progress flight works like this:

Upload

Photos into the site

Upload from the web, the desktop application or the phone. Naming the site when the stitch starts tags every result with that site, so it is listed beside every earlier flight of the same place.

Check

Checked before anyone pays

Photo count, camera angle, GPS coverage and separate flight groups are checked, flight height sets the expected map resolution, and, in the cloud and data center editions, the price is shown up front and a failed or cancelled job is refunded in full.

Stitch

Orthomosaic, surface and terrain models

Plus a point cloud and, if asked for, a 3D model. Large sites are processed in sections and merged. A stitch report is filed with the results.

Review

Date by date in the Site Navigator

Fade, swipe or blink between dates, measure, compute volumes and place findings.

Report

To the owner, the lender, the team

A live, read-only site link, a PDF report, or deliverables pushed to Procore or Autodesk Forma.

Reports owners can read

Live links instead of email attachments

A Site Navigator link gives an owner's representative or lender a live view: the dates and layers you choose, optionally every future flight, with an optional password and expiry, revocable at any time. They can measure and compare dates on the full-resolution data but cannot save anything. By default they can only view; you can also let them download the shared maps, and choose whether to include the source photos. See the Sharing and delivery paper.

Told when something changes

From a comparison on a site, Alert me sets up a standing watch: when a new flight changes the net volume (up, down or either way), the material added, or the material removed beyond a threshold you set, you and up to 10 other Omniris users who can open the site are emailed. Alerts are checked every six hours. The Site management paper covers sites, the Site Navigator and alerts in full.

Earthwork, stockpiles and cut/fill

Earthwork is where a drone survey earns its keep, and where a careless volume costs the most. In Omniris a volume is computed cell by cell over the surface model at its full resolution: material above the base is cut, space below it is fill, and the difference is the net. Results show in feet, acres, cubic yards and US tons unless you choose metric; printed reports show both.

Choosing the base

BaseUse it for
Triangulated (default)A base that follows sloping ground under a pile, through the heights at the boundary's corners
Best-fit planeRamps and evenly sloped pads
Lowest pointFlat pads (one corner in a rut drops the whole base)
Highest pointTrenches, ponds and voids
Custom elevationA known floor, bench or subgrade height you enter
Design surfaceCut and fill against the design: an imported design model, or a DXF, LandXML or design GeoTIFF file
A comparison is only as good as the alignment

If two surveys are offset from each other, the offset looks like cut and fill. Omniris grades every pair of dates for how well they line up — same ground control, or a later flight aligned to the earlier one — and labels an unaligned pair's result an estimate. Controlled flights on both dates are the fix.

Design files as the volume base

Three ways to bring the design surface in:

The same design surface drives Compare's Design mode in the Site Navigator: a red-and-blue cut/fill map of where the ground is above the design (material to remove) and below it (material to place), with the share of the survey area the chosen design objects cover.

Grading, drainage and topography for the design team

The Stitching paper covers stitching, measuring, volumes and terrain analysis in full.

Design versus as-built

State transportation departments already fly drones for as-built surveys, including immediately after construction [2]. Omniris makes the design a first-class part of the site, not a picture laid on top.

Bringing in the design

FormatWhat Omniris reads
IFC (the open BIM format), including IFC 4.3 for roads and railEvery building or infrastructure element, with its properties, quantities and 3D shape; placed on the earth when the file records where it sits
AutoCAD DWG and DXF3D faces and shapes as surfaces, lines as lines, one object per drawing element
MicroStation DGN (V8 and V7, 2D and 3D)The same, one object per design element

Coordinates are stated, never guessed

The design and the drone survey are usually in different coordinate systems, and the gap can be several feet sideways and tens of feet in height. Omniris requires both sides to say what they are:

"Is it at grade?"

For objects with design heights — slabs, pads, pavements, subgrade — Omniris measures how much of each object's footprint is at the design height within a tolerance. The site default is ±0.1 ft (about 1.2 in / 3 cm), adjustable per object type. Only survey-grade flights are graded (RTK with network or known-point corrections, or surveyed ground control); if the tolerance is tighter than the flight can measure, the object is marked "survey too coarse for this tolerance" rather than given a number.

The Design, progress and integrations paper describes design import, coordinates and grading in full.

Schedule and progress

Schedules already have a place for measured progress. In Primavera P6, an activity whose percent-complete type is Physical takes a percent complete the user records (or one calculated from activity steps), separate from duration or units [11]; Microsoft Project's Earned Value Method field can use Physical % Complete instead of % Complete to calculate earned value [12]. What is usually missing is the measurement. Omniris supplies it, from the flights.

1

Import the schedule

Primavera P6 (XER or P6 XML) or Microsoft Project (.mpp or Project XML), with WBS, dates, links, calendars, costs and baselines. Updates are matched activity by activity; removed activities keep their history.

2

Link activities to the design

Pick objects on the map, draw around an area, or match by a rule (for example layer name against activity code). Each link says how the object counts: by count, length, area, volume, mass or percent.

3

Measure each flight

Elevation at grade on survey-grade flights; detected present where AI detection was run (for example formwork in a footprint); or manual, from the web, the desktop or a phone on site — the method for curbs, pipe and poles.

4

A person approves

Measured values are proposals until someone approves them. One approval covers a flight and is sealed into the chain of custody with a fingerprint of exactly what was approved. Manual entries count once saved.

5

Roll up

Percent complete against planned through every WBS group, a forecast finish from the rate actually achieved, SPI(t), and earned value when the schedule carries costs (actual cost and CPI only when it carries actuals).

6

Back to the schedule

Export to schedule writes physical percent complete, actual start and actual finish into a copy of your schedule file, with a change list of every value written. Files are edited, not rebuilt (an .mpp comes back as Project XML); your scheduler imports the file.

What the scheduling tool will use

P6 uses physical percent complete only for activities whose percent-complete type is Physical [11]; Microsoft Project uses it for earned value only on tasks set to the Physical % Complete method, which is not the default [12]. The change list flags every activity set any other way.

For data center and other repetitive builds

Thousands of near-identical objects — piers, equipment pads, slabs, duct-bank runs — are linked to the activities that build them by rule rather than one by one, measured on every survey-grade flight, and rolled up across the campus. In the Gantt chart, an owner's representative can see the percent complete the schedule file reports beside the measured progress, with every approval on the record.

Pay applications

A pay application's continuation sheet (AIA G703) lists a percent complete for every schedule-of-values line, so that the architect can certify the payment due [19]. Omniris gives that reviewer measured, approved progress per schedule activity and earned value. Where pay lines and schedule activities differ, the project team maps one to the other.

Inspection, safety and stormwater

Not every construction flight is about quantities. Half of the drone-flying contractors in the ABC survey use drones for inspections [1], and FHWA points to routine checks such as flying a programmed path over silt fence after rain, and high-risk ones such as crane and falsework construction [3]. In Omniris, what a flight finds becomes a finding.

Findings: from "I saw it on the map" to a closed item

The Findings paper describes the workflow in full.

Stormwater and erosion control

A drone flight can cover the perimeter controls, inlets and stabilised areas that the CGP requires a qualified person to inspect every 7 days or after a qualifying storm [4]. Omniris supports that inspection:

The inspection report the permit requires, and the judgement of the qualified person, stay with your stormwater programme.

Site logistics and safety

A dated, measurable map of the whole site each week shows laydown areas, haul roads, access points, fencing and open excavations as they are, not as the logistics plan drew them. AI detection finds and outlines the objects you name in plain words — equipment, vehicles, containers, materials — across photos or a whole orthomosaic, and a person checks and corrects the result before anyone relies on it (see the AI detection paper). AI change lists what appeared or disappeared between two dates.

Façades, roofs and structures

A measurable 3D mesh of a building, a thermal map of a roof, and findings pinned to the exact spot on either. Thermal maps carry real surface temperatures you can click and outline; roof surveys use a preset that follows ASTM C1153, reporting warm areas on a flight after sunset as moisture candidates (see the Thermal imaging paper).

3D models, 360 panoramas and measuring

ProductWhat it is forMeasurable?
3D meshA photo-textured model at real-world scale, with surface and terrain models alongside: progress, façades, as-built recordsYes — in 3D on the model, and on the 2D map from its surface and terrain models
Gaussian splatA photo-real copy that keeps glass, foliage and fine detail. Stakeholder walk-throughs and a visual recordNo — it has no reliable real-world scale
360° panoramaA DJI sphere panorama stitched into a 360° view, aligned to gravity and northNo — for looking
LiDAR point cloudLAS/LAZ surveys classified into ground, vegetation, buildings, wires and towers, with terrain, surface and contour productsIn the point-cloud viewer; the map's volume and comparison tools work on photo surveys, not LiDAR height maps

Measuring in 3D

A 3D model made in a stitch is placed with that stitch's ground control, or with the photos' GPS when there is none. A mesh built as its own 3D project takes its scale and position from the photos' GPS only; with a standard (non-RTK) drone the whole model can sit several feet from its true position without changing anything measured on it. The Digital twins paper and the LiDAR and point cloud paper cover these products.

Accuracy and standards

What the industry measures accuracy against

What Omniris gives you

ToolWhat it does
Ground control pointsImport surveyed coordinates from common survey equipment and software or CSV, in your survey's coordinate system; ArUco coded targets found automatically and confirmed by you; heights on a known reference converted to one reference before the stitch
CheckpointsSurveyed points held out of the fit and measured on the delivered map: error east, north and up for each, horizontal, vertical and 3D RMSE, the mean error in each direction, and which checkpoints lie outside the area the control encloses. Checkpoints marked later are measured on the finished map without re-stitching, at no charge
Accuracy classA stitch's ground control is labelled by its loosest point's stated horizontal accuracy: survey-grade (4 in / 0.1 m or better), survey control (up to 3.3 ft / 1 m), or basemap-grade (looser, or picked from imagery); a stitch aligned to an earlier flight is labelled so, and control with no stated accuracy gives "accuracy class unknown". Checkpoint accuracy leads the stitch report's ground-control results when checkpoints were used
Without surveyed pointsGround reference points picked on satellite imagery (assumed good to about ±10 ft / 3 m horizontally and ±33 ft / 10 m vertically, and labelled basemap-grade) or alignment to an earlier flight of the site
What an accuracy figure claims

Omniris reports measured checkpoint errors and RMSE; it does not test them against an ASPRS accuracy class, count checkpoints against the standard's minimum, or certify a map. Errors at control points show how well the map fits the points it was fitted to, not its accuracy elsewhere — checkpoints are that test. Without ground control, positions come from the drone's own GPS and the stitch report says absolute accuracy cannot be stated from that flight alone.

Design grading uses whichever is looser, the accuracy stated for the control or the vertical accuracy the checkpoints measured, so a checkpoint can only tighten what is graded, never loosen it.

Evidence and records

Construction disputes — delay claims, quantity disputes, change orders, defect claims — turn on what the site looked like on a given day and who said what about it. Omniris keeps the flights and everything made from them as evidence, not as loose files:

The Evidence integrity paper describes custody, certificates, holds and encryption in full.

Getting the flights flown

In the United States, commercial flights of small drones are flown under 14 CFR Part 107, which requires a remote pilot certificate (or direct supervision by a certificated remote pilot in command) and limits altitude to 400 ft above ground level, unless the drone is within 400 ft of a structure and no more than 400 ft above its top [16]. Omniris plans the flight and keeps the record; the pilot flies it in the aircraft's own app.

Plan the mission

Airspace, weather and pre-flight

The Mission planning paper covers planning, airspace and checklists.

Hiring a pilot through the marketplace

In the cloud and data center editions, a contractor or owner without its own pilot can post a job: draw the site, pick deliverables (photos, video, orthomosaic, 3D model, thermal, multispectral, LiDAR, raw data), and set the schedule and point of contact. Approved pilots whose travel radius covers the site are notified and can apply; the client accepts one application, or sends an offer straight to a pilot who has delivered before. Results are delivered into the job's folder and accepted or rejected with notes.

The marketplace, payments and payouts are part of the cloud and data center editions only; on-premises installations fly with their own pilots.

In the field

The Omniris Pilot phone app, for iPhone and Android, carries the jobs, the pre-flight checklist (filed with the job as a permanent record), the findings assigned to you and site progress recording. Work done without signal is saved on the phone and sent once it reconnects. See the Field app paper.

Integrations and delivery

Procore and Autodesk Forma

Connect your Procore or Autodesk account from the Integrations tab of your Account page (an organization's account is connected by one of its managers), then link each site to a Procore project, or to a Forma project and folder.

ProcoreAutodesk Forma
Sending deliverablesAny file or folder — orthomosaics, elevation models, reports, schedule exports — to the project's Documents, large files includedThe same, to a Forma folder; a file with the same name becomes a new version
Bringing files inPick a design or schedule file from Procore DocumentsPick a design or schedule file from Forma
FindingsTwo-way with Observations: new items, status, assignee, comments and pictures; title and description are sent when an item is created, and edits made in Procore come backTwo-way with Issues: the same
How fastAs they happen, through Procore's change notifications, with a check every 5 minutes as a fallbackA check every 5 minutes
SchedulesA schedule in Procore can be read into the Progress panel; progress goes back as an exported P6 (XER) file for your scheduler to importSchedules come in as files; progress goes back as an exported file
Omniris inside the other systemAn Omniris panel inside Procore showing the site's map, flight comparison and progress — only what that person can already see in Omniris—

A change that arrives from Procore or Forma is never echoed back, and each change is applied once. A Procore Observation or Forma Issue created there arrives as a finding marked "Location needed" until someone places it on the map, because they carry no map position. Encrypted files are skipped and listed as "Protected — not sent" unless someone allowed to open them releases them on purpose.

Other ways out

Cloud, data center and on-premises

The capabilities in this paper run on every Omniris edition:

EditionProcessingNotes for construction
Omniris cloud on Microsoft AzureA processing machine sized for each job, started for it and released after itMarketplace, recurring jobs and payments included
Omniris cloud on Google CloudThe sameThe same
Omniris data center editionOmniris' own processing serversMarketplace, recurring jobs and payments included
On-premises, on your hardwareYour site's own processing servers; photos and results stay on siteNo marketplace or payments: you fly with your own pilots. You register your own Procore and Autodesk apps, and the site must be served over HTTPS to connect them. An installation connected to the Omniris cloud can send a single stitch there when it chooses.

On-premises suits owners and builders whose site imagery must stay inside their own network. Where processing runs on a fixed set of machines (the data center edition and on-premises), if no machine is large enough for a 3D model of the selected photos, the stitch dialog turns the 3D options off and says why, rather than accepting a job that could never run.

What the results claim, and what they don't

Construction numbers end up in pay applications, claims and as-built records, so Omniris states what each result is:

Not a survey certificate

Omniris provides measured quantities, measured accuracy and the record behind them. Whether a survey meets a contract specification or an agency standard, and what a number means for a payment or a claim, is for the surveyor, engineer or owner who relies on it. The reports give both the numbers and how they were measured so that judgement can be made.

Sources

  1. Associated Builders and Contractors, "ABC Report: 36% of Contractor Members Utilize Drones on Jobsites," August 17, 2026 (survey conducted May 1–15, 2026), and the full "ABC Drone Usage Survey Report." abc.org · report (PDF)
  2. National Academies of Sciences, Engineering, and Medicine, Use of Unmanned Aerial Systems for Highway Construction, NCHRP Synthesis 578, 2022, doi:10.17226/26546: Summary (survey results) and Chapter 4, Case Examples (Oregon DOT OR 82 Minam Curve). nationalacademies.org/publications/26546 · chapter 4
  3. Federal Highway Administration, Every Day Counts (EDC-5), "Unmanned Aerial Systems (UAS)" fact sheet. fhwa.dot.gov
  4. US EPA, 2022 NPDES Construction General Permit, Part 4 (Inspection Requirements), §4.1–4.3 (unchanged in the 2025 modified permit). epa.gov (permit PDF)
  5. US EPA, "2022 Construction General Permit (CGP)" (final modification, Federal Register, April 15, 2025; proposed 2027 CGP, Federal Register, August 3, 2026). epa.gov
  6. US Geological Survey, National Geospatial Program, "Adopt updated accuracy standards" (changes in ASPRS Positional Accuracy Standards, Edition 2). usgs.gov
  7. LIDAR Magazine, "The ASPRS Positional Accuracy Standards, Edition 2," October 6, 2023. lidarmag.com
  8. Clemson University, Center for Connected Multimodal Mobility, Unmanned Aircraft Systems (UAS) Impact on Operational Efficiency and Connectivity (South Carolina DOT), December 2019. rosap.ntl.bts.gov
  9. North Carolina DOT Photogrammetry Unit, "UAS Project with Non-Metric Camera for Earthwork Volumes" (project report series; example: R-2582A borrow pit). connect.ncdot.gov
  10. Kokamägi, K., Türk, K. and Liba, N., "UAV photogrammetry for volume calculations," Agronomy Research 18(3), 2020. dspace.emu.ee
  11. Oracle, Primavera P6 EPPM Help, "Percent Complete Columns of the Activity Table." docs.oracle.com
  12. Microsoft Support, "Earned Value Method (task field)," Microsoft Project. support.microsoft.com
  13. Electrical Marketing, "Data Centers Still Sizzling…," reporting US Census Bureau construction spending for April 2026. electricalmarketing.com
  14. Associated General Contractors of America, "Construction Spending July 2026," from US Census Bureau construction spending data. agc.org
  15. Eagle Point Software, "Autodesk Construction Cloud Rebrands to Autodesk Forma," March 26, 2026. eaglepoint.com
  16. 14 CFR Part 107, Small Unmanned Aircraft Systems, including §107.12 (remote pilot certificate) and §107.51(b) (altitude). ecfr.gov
  17. NOAA National Geodetic Survey, "New Datums." geodesy.noaa.gov
  18. "Unmanned Aircraft Systems and Surveying," presentation on the North Carolina Board of Examiners for Engineers and Surveyors' position, citing NC G.S. 89C-3(7) and 89C-23. connect.ncdot.gov
  19. American Institute of Architects, "Instructions: G703–1992, Continuation Sheet," AIA Contract Documents. help.aiacontracts.com

Glossary

BIM / IFC
Building information modelling: a 3D design in which every element carries its own data. IFC is the open file format for exchanging those models.
Checkpoint
A surveyed point left out of the map's fit and used only to measure how accurate the map is there.
Cut / fill
Material above the base or design (to remove) and space below it (to fill). Net is the difference.
CGP / SWPPP
EPA's Construction General Permit for stormwater, and the Stormwater Pollution Prevention Plan a covered site keeps and inspects against.
Design surface
The top faces of chosen design objects, or a design DXF, LandXML or GeoTIFF, used as the base a survey is measured against.
DSM / DTM
Surface model (the top of everything, including equipment and structures) and terrain model (bare ground).
Ground control point (GCP)
A marker on the ground whose position has been surveyed, used to pin the map to the survey.
LAANC
The FAA's Low Altitude Authorization and Notification Capability, which grants near-airport drone authorizations up to set ceilings.
Orthomosaic
One map-accurate image stitched from many overlapping drone photos, so distances and areas measured on it are true.
Physical percent complete
A schedule's measure of work physically in place, entered rather than calculated from duration.
RMSE
Root mean square error: the standard summary of checkpoint errors, horizontal (RMSEH) and vertical (RMSEV).
RTK
Real-time kinematic positioning: satellite positions corrected in flight by a base station or network, far more precise than the drone's own GPS alone.
SPI(t)
Earned-schedule performance index: earned schedule divided by actual time; above 1 is ahead, below 1 behind.
State Plane
The US system of map projections, one or more per state, in which most civil designs are drawn.
Survey-grade flight
A flight tied to known survey points: RTK with network or known-point corrections, or surveyed ground control.
WBS
Work breakdown structure: how a schedule groups its activities, for example by area, phase or trade.
Omniris · Construction vertical paper, October 2026. This paper describes product capabilities; industry figures are from the numbered sources.